Duty to Consult: 2022-2024 ISO Energy Ltd. – Mineral Exploration Program – Radio Project
What type of activities will occur?
50 drill holes on land and ice.
Geophysical Survey, with 40km of line cutting.
Clearing for drill pads.
10km of trails.
Temporary work camp.
Area will be accessed from the seasonal road near Points North and extend from Rio Tinto's Roughrider Core facility by opening up an existing trail with a low impact skidder to access the area and drilling locations and hand tools will be used for any clearing required within 100 meters of a waterbody.
Some of the work may be carried out with helicopter and/or float plane in the summer months which may require temporary dock(s).
Project work is scheduled for January 2022 to December 2024.
When will these activities occur (Permit Length)? If approved, June 2021 till December 2024.
If you have any comments or concerns, please contact your local Community Land Technician or Environmental Land Use Planner at 306-477-1251.