Duty to Consult: Mustang Energy’s Spur Project
Who? Mustang Energy
Where? The Spur Project is located approximately 40 km southeast of Key Lake Operation
What type of activities will occur? Mineral exploration activities, including:
• The crew will access the property via float or ski equipped aircraft, helicopter and along trails once on site
• The drilling crew will consist of up to 18 people on site for a duration of 48 weeks
• The geophysical crew will consist of up to 5 people on site for a duration of 6 weeks
• The line cutting crew will consist of up to 5 people on site for a duration of 6 weeks
• One temporary work camp is being requested, occupying less than 0.5 hectares
• Up to 20 drill holes are being proposed, with 10 on land and 10 on ice
• Helicopter pads may be established to assist with the drilling program
• Approximately 20 km of ice roads, 3 km of new trails and 50 km of existing trails will be utilized
• Up to 70 km of new line will be established for the geophysical program
When will these activities occur (Estimated Permit Length)? May 2025 to April 2028