Duty to Consult: 2022-2023 Orano Canada Inc. Kernaghan/ Bell Project – Geophysics & Line cutting
What type of activities will occur?
1. The project consists of line cutting and line slashing of up to 50 kilometers of line not exceeding 1.5-meter width.
2. Line cutting will be carried out with hand tools either chainsaw or axe.
3. A small temporary camp will be required on a historic drill site to accommodate personnel while carrying out ground geophysical surveys.
4. The area is accessible by float/ski plane or by snowmobile/UTV or vehicle if snow is removed from the existing trail.
5. The project work will be carried out over a 4-week period between December 1, 2021 and June 30, 2023.
When will these activities occur (Permit Length)? If approved, December 2021 till June 2023.
If you have any comments or concerns, please contact your local Community Land Technician or Environmental Land Use Planner at 306-477-1251.