Duty to Consult: 2022-2024 ISO Energy Ltd. – Mineral Exploration Program – Western Larocque East Project
What type of activities will occur?
1. 50 drill holes on land and ice.
2. Geophysical surveys with 200 km of line cutting.
3. 10km of new trail.
4. Three temporary work camps.
5. The area will be accessed from KM 60 on the Athabasca Seasonal Road northwest of Points North by opening up an existing trail with a low impact skidder to access the area and drilling locations and hand tools will be used for any clearing required within 100 meters of a waterbody. Some of the work may be carried out with helicopter and/or float plane in the summer months which may require temporary dock(s).
6. Work will occur January 2022 to December 2024
When will these activities occur (Permit Length)? If approved, July 2021 till December 2024.
If you have any comments or concerns, please contact your local Community Land Technician or
Environmental Land Use Planner at 306-477-1251.