Duty to Consult: SaskPower’s W3B Rebuild Project
Who? SaskPower
Where? The W3B Rebuild Project is located near Uranium City and will extend between the Beaverlodge Switching Station and reconnect with the W3B line
What type of activities will occur? Mineral exploration activities, including:
• All transmission line rebuild activities will occur within a 60 m right-of-way (ROW)
• The ROW will be cleared by hand
• Two (2) areas off the ROW require clearing (width of 8-10 m) to allow for installation of counterpoise wire
• The ROW will be accessed by truck, and helicopter when truck is not feasible
• Salvaging 41 structures along the ROW between fall of 2025 and spring of 2026
When will these activities occur?: September 2024 to September 2026