Duty to Consult: SaskPower’s HDD-511 Vegetation Project

Who? SaskPower

Where? The project is located from Hidden Bay to Wollaston Post along Wollaston Lake

What type of activities will occur? Mechanical clearing and herbicide application:

 Year 0: mechanical vegetation clearing has already been completed to remove all tall growing non-compatible

vegetation along the length of the ROW.

 Year 2: Foliar berbicide application is completed as required along the length of the ROW to control the

regrowth.

 Year 5: Selective herbicide application and mechanical clearing will be completed based on the regrowth.

When will these activities occur (Permit Length)? March 2024 – March 2030