Duty to Consult: Purepoint’s Edge Project
Who? Purepoint
Where? The Edge Project is located approximately 82 km northwest of Wollaston Lake
What type of activities will occur? Mineral exploration activities, including:
Access
• Access to site will be by helicopter, float plane, boat or on foot depending on the location
• No trail clearing will be required
Temporary Work Camp
• 1 Temporary work camp location has been requested
Diamond Drilling
• Maximum of 20 drill locations; no ice drilling
• Maximum drill pad size – 30 m x 30 m (900 m²)
• Clearing in relation to a helicopter supported drilling program will be hand cleared
• Helicopter will be required; helicopter pads will utilize open areas to minimize clearing
Soil Sampling and Ambient Noise Tomography
• Soil samples will be taken using trowel or soil auger
• Ambient Noise Tomography will not cause any disturbance
• Access will be on foot or by helicopter
• No new trails will be cleared
When will these activities occur (Estimated Permit Length)? 2025 to 2027