Duty to Consult: 2022-2023 Ground Geophysics Permit Application for the Goldfields West Project
What type of activities will occur?
1. The proposed Fortune Bay project includes line-cutting and geophysical surveys, and is estimated to last approximately 6 weeks.
2. Proposed work consists of 22 km of new cut-lines, 40 km of historic cut-line refurbishment, both with a maximum width of 1.5 meters, and up to 60 km of picketing.
3. This project will also include ground and airborne geophysical surveys.
Permit Length: If approved, January 2022 to April 2023.