Duty to Consult: SaskPower’s HDD-511 Project

Who? SaskPower

Where? The transmission line that serves Hatchet Lake, from Highway 905 to Wollaston Lake

Post

What type of activities will occur? Maintenance of power transmission line, including:

• Clearing of vegetation

• Pole straightening and replacement

• Installation of new poles, hardware, guy cables, anchors, and gang-operated switch

When will these activities occur (Permit Length) January 2024 to March 2026